PROJECTTASKPLANNEDSTARTDATE

Overview

The PROJECTTASKPLANNEDSTARTDATE function returns the planned start date of a project task.

Syntax

=PROJECTTASKPLANNEDSTARTDATE(
    ConnectionName,
    Project,
    Task
)

Arguments

The PROJECTTASKPLANNEDSTARTDATE function uses the following arguments:


Argument

Required/Optional

Description

ConnectionName

Optional

Provide one of the following values:

OR

Omit the argument to return results for all compatible connections with default aggregation settings.

Project

Required

The Project to include

Task

Required

The ID of the Task to include

Example

=PROJECTTASKPLANNEDSTARTDATE(
    "Demo",
    "FIXEDP01",
    "01TASK"
)


Description

Returns the planned start date of 01TASK task of the FIXEDP01 project.


Result

41456

The results are returned as a serial number - to match Excel's default treatment for dates. The cell can be formatted to any date format desired.