PROJECTTASKSTARTDATE function
Created by Harry Lewis, Modified on Tue, 16 Jul at 9:34 AM by Gabriel Michaud
Applies to
- Velixo NX
- Velixo Classic
- Acumatica, MYOB Acumatica, Cegid
Description
The PROJECTTASKSTARTDATE function returns the start date of a project task.
Syntax
PROJECTTASKSTARTDATE(Connection, Project, ProjectTask)
Parameters
The PROJECTTASKSTARTDATE function uses the following parameters (see our article on filtering Velixo functions):
\
Parameter | Required/Optional | Description |
Connection | Required | The name of the connection as configured in the Connection Manager |
Project | Required | The Project(s) to include |
ProjectTask | Required | The ID(s) of the Task(s) to include |
Example
=PROJECTTASKSTARTDATE("Demo","FIXEDP01", "01TASK")
Description
Returns the start date of 01TASK task of the FIXEDP01 project.
Result
41456
Note that the results are returned as a serial number - to match Excel's default treatment for dates. The cell can be formatted to any date format desired. |
Applies to:
PM Module
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article