PROJECTTASKENDDATE
Overview
The PROJECTTASKENDDATE function returns the end date of a project task.
Syntax
=PROJECTTASKENDDATE(
ConnectionName,
Project,
Task
)
Arguments
The PROJECTTASKENDDATE function uses the following arguments:
Argument | Required/Optional | Description |
| Optional | Provide one of the following values:
OR Omit the argument to return results for all compatible connections with default aggregation settings. |
| Required | The ID of the Project to include |
| Required | The ID of the Task to include |
Example
=PROJECTTASKENDDATE(
"Demo",
"FIXEDP01",
"01TASK"
)
Description
Returns the end date of the 01TASK task in project FIXEDP01.
Result
41470