PROJECTREVISEDCOMMITTEDAMOUNT function
Created by Harry Lewis, Modified on Tue, 16 Jul at 9:34 AM by Gabriel Michaud
Applies to
- Velixo NX
- Velixo Classic
- Acumatica, MYOB Acumatica, Cegid
Description
The PROJECTREVISEDCOMMITTEDAMOUNT function calculates the revised committed amount of one or more projects and tasks.
Syntax
PROJECTREVISEDCOMMITTEDAMOUNT(Connection, Project, Task, AccountGroup, CostCode, InventoryItem, UseProjectCurrency)
Parameters
The PROJECTREVISEDCOMMITTEDAMOUNT function uses the following parameters (see our article on filtering Velixo functions):
Parameter | Required/Optional | Description |
Connection | Required | The name of the connection as configured in the Connection Manager |
Project | Required | The Project(s) to include |
Task | Optional | The Task(s) to include |
AccountGroup | Optional | The Account Group(s) to include |
CostCode | Optional | The Cost Code(s) to include |
InventoryItem | Optional | The Inventory Item(s) to include |
UseProjectCurrency | Optional | TRUE/FALSE value indicating if the amount should be returned in the project's currency (default = FALSE) |
Example
=PROJECTREVISEDCOMMITTEDAMOUNT("Demo", "20171001", "03", "SUB", "03460", "<N/A>",FALSE)
Description
Calculates the revised committed amount of task 03 in the 20171001 project (filtered by the specified AccountGroup, CostCode, and InventoryItem) and returns the value in the default currency.
Result
1485
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article