PROJECTTASKPLANNEDSTARTDATE function

Created by Harry Lewis, Modified on Tue, 16 Jul at 9:34 AM by Gabriel Michaud

Applies to

  • Velixo NX
  • Velixo Classic
  • Acumatica, MYOB Acumatica, Cegid


Description

The PROJECTTASKPLANNEDSTARTDATE function returns the planned start date of a project task.

  

Syntax

  PROJECTTASKPLANNEDSTARTDATE(Connection, Project, ProjectTask)

  

Parameters

The PROJECTTASKPLANNEDSTARTDATE function uses the following parameters:

 

Parameter

Required/Optional

Description

Connection

Required

The name of the connection as configured in the Connection Manager

Project 

Required

The Project to include

ProjectTask 

Required

The ID of the Task to include

Example

=PROJECTTASKPLANNEDSTARTDATE("Demo","FIXEDP01", "01TASK")

 

Description

Returns the planned start date of 01TASK task of the FIXEDP01 project.

 

Result

41456

 

Note that the results are returned as a serial number - to match Excel's default treatment for dates. The cell can be formatted to any date format desired.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article