PROJECTREVISEDBUDGETAMOUNT
Overview
The PROJECTREVISEDBUDGETAMOUNT function calculates the revised budgeted amount of one or more project(s) and task(s).
Syntax
=PROJECTREVISEDBUDGETAMOUNT(Connection, Project, Task, AccountGroup, CostCode, InventoryItem, UseProjectCurrency)
Arguments
The PROJECTREVISEDBUDGETAMOUNT function uses the following arguments (see our article on filtering Velixo functions):
Argument | Required/Optional | Description |
| Required | The name of the connection as configured in the Connection Manager |
| Required | The Project(s) to include |
| Optional | The Task(s) to include |
| Optional | The Account Group(s) to include |
| Optional | The Cost Code(s) to include |
| Optional | The Inventory Item(s) to include |
| Optional |
|
Example
=PROJECTREVISEDBUDGETAMOUNT("Demo","FIXEDP01","",,,"", TRUE)
Description
Calculates the revised budgeted amount of the FIXEDP01 projects and task(s) and return the value in the project's defined currency.
Result
16000