PROJECTTASKENDDATE function
Created by Harry Lewis, Modified on Tue, 16 Jul at 9:34 AM by Gabriel Michaud
Applies to
- Velixo NX
- Velixo Classic
- Acumatica, MYOB Acumatica, Cegid
Description
The PROJECTTASKENDDATE function returns the end date of a project task.
Syntax
PROJECTTASKENDDATE(Connection, Project, ProjectTask)
Parameters
The PROJECTTASKENDDATE function uses the following parameters:
Parameter | Required/Optional | Description |
Connection | Required | The name of the connection as configured in the Connection Manager |
Project | Required | The ID of the Project to include |
ProjectTask | Required | The ID of the Task to include |
Example
=PROJECTTASKENDDATE("Demo","FIXEDP01", "01TASK")
Description
Returns the end date of the 01TASK task in project FIXEDP01.
Result
41470
Note that the results are returned as a serial number - to match Excel's default treatment for dates. The cell can be formatted to any date format desired. |
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article