Description
The PROJECTTASKPLANNEDSTARTDATE function returns the planned start date of a project task.
Syntax
PROJECTTASKPLANNEDSTARTDATE(Connection, Project, ProjectTask)
The PROJECTTASKPLANNEDSTARTDATE function uses the following parameters:
Parameter | Required/Optional | Description |
Connection | Required | The name of the connection as configured in the Connection Manager |
Project | Required | The Project to include |
ProjectTask | Required | The ID of the Task to include |
Example
=PROJECTTASKPLANNEDSTARTDATE("Demo","FIXEDP01", "01TASK")
Description
Returns the planned start date of 01TASK task of the FIXEDP01 project.
Result
41456
Note that the results are returned as a serial number - to match Excel's default treatment for dates. The cell can be formatted to any date format desired. |
Applies to
PM Module