Requires Acumatica 2019 or higher | MYOB Advanced 2019.1 or higher

Description

The PROJECTFORECASTQUANTITY function calculates the original forecasted quantity of one or more project(s) and task(s).

Syntax

PROJECTFORECASTQUANTITY(Connection, Project, Revision, Task, AccountGroup, 
CostCode, InventoryItem, FromPeriod, ToPeriod)

The PROJECTFORECASTQUANTITY function uses the following parameters (see our article on Filtering Velixo functions):

Parameter

Required/Optional

Description

Connection

Required

The name of the connection as configured in the Connection Manager

Project

Required

The Project(s) to include

Revision

Required

The Project Revision to include

Task

Optional

The Task(s) to include

AccountGroup

Optional

The Account Group(s) to include

CostCode

Optional

The Cost Code(s) to include

InventoryItem

Optional

The Inventory Item(s) to include

FromPeriod

Required

Starting Financial period in MM-YYYY format

ToPeriod

Required

Ending Financial period in MM-YYYY format

Example

=PROJECTFORECASTQUANTITY("Demo","BUDGETBYM","2","01","MATERIAL",,
"AACOMPUT01", "03-2019","03-2019")

Description

Calculates the forecasted quantity for revision 2 of the forecast of BUDGETBYM, during the third financial period of 2019 and filtered on task 01, account group MATERIAL and inventory item AACOMPUT01

Result

1.00

Applies to

PM Module

Did this answer your question?