Description

The PROJECTCOSTATCOMPLETION function calculates the cost at completion of one or more projects and tasks.

Syntax

PROJECTCOSTATCOMPLETION(Connection, Project, Task, AccountGroup,
CostCode, InventoryItem, UseProjectCurrency)

The PROJECTCOSTATCOMPLETION function uses the following parameters (see our article on Filtering Velixo functions):

Parameter

Required/Optional

Description

Connection

Required

The name of the connection as configured in the Connection Manager

Project

Required

The Project(s) to include

Task

Optional

The Task(s) to include

AccountGroup

Optional

The Account Group(s) to include

CostCode

Optional

The Cost Code(s) to include

InventoryItem

Optional

The Inventory Item(s) to include

UseProjectCurrency

Optional

TRUE/FALSE value indicating if the amount should be returned in the project's currency (default = FALSE)

Example

=PROJECTCOSTATCOMPLETION("Demo","FLDEVELOP1","L01", "SUB", "09200", "<N/A>",TRUE)

Description

Calculates the cost at completion of task L01 in project FLDEVELOP1 (filtered by the specified AccountGroup, CostCode, and InventoryItem) and returns the value in the Project's defined currency.

Result

0

Applies to

PM Module