Description
The PROJECTCOSTATCOMPLETION function calculates the cost at completion of one or more projects and tasks.
Syntax
PROJECTCOSTATCOMPLETION(Connection, Project, Task, AccountGroup,
CostCode, InventoryItem, UseProjectCurrency)
The PROJECTCOSTATCOMPLETION function uses the following parameters (see our article on Filtering Velixo functions):
Parameter | Required/Optional | Description |
Connection | Required | The name of the connection as configured in the Connection Manager |
Project | Required | The Project(s) to include |
Task | Optional | The Task(s) to include |
AccountGroup | Optional | The Account Group(s) to include |
CostCode | Optional | The Cost Code(s) to include |
InventoryItem | Optional | The Inventory Item(s) to include |
UseProjectCurrency | Optional | TRUE/FALSE value indicating if the amount should be returned in the project's currency (default = FALSE) |
Example
=PROJECTCOSTATCOMPLETION("Demo","FLDEVELOP1","L01", "SUB", "09200", "<N/A>",TRUE)
Description
Calculates the cost at completion of task L01 in project FLDEVELOP1 (filtered by the specified AccountGroup, CostCode, and InventoryItem) and returns the value in the Project's defined currency.
Result
0
Applies to
PM Module